IT-Tests.com is a website specifically provide the certification exam information sources for IT professionals. Through many reflects from people who have purchase IT-Tests's products, IT-Tests.com is proved to be the best website to provide the source of information about certification exam. The product of IT-Tests.com is a very reliable training tool for you. The answers of the exam exercises provided by IT-Tests.com is very accurate. Our IT-Tests's senior experts are continuing to enhance the quality of our training materials.
According to the research of the past exams and answers, IT-Tests.com provide you the latest Oracle 1Z1-466 exercises and answers, which have have a very close similarity with real exam. IT-Tests.com can promise that you can 100% pass your first time to attend Oracle certification 1Z1-466 exam.
Exam Code: 1Z1-466
Exam Name: Oracle (Project Lifecycle Management Essentials)
Free One year updates to match real exam scenarios, 100% pass and refund Warranty.
Total Q&A: 98 Questions and Answers
Last Update: 2014-02-16
There are different ways to achieve the same purpose, and it's determined by what way you choose. A lot of people want to pass Oracle certification 1Z1-466 exam to let their job and life improve, but people participated in the Oracle certification 1Z1-466 exam all knew that Oracle certification 1Z1-466 exam is not very simple. In order to pass Oracle certification 1Z1-466 exam some people spend a lot of valuable time and effort to prepare, but did not succeed.
As long as you need the exam, we can update the Oracle certification 1Z1-466 exam training materials to meet your examination needs. IT-Tests's training materials contain many practice questions and answers about Oracle 1Z1-466 and they can 100% ensure you pass Oracle 1Z1-466 exam. With the training materials we provide, you can take a better preparation for the exam. And we will also provide you a year free update service.
In IT-Tests's website you can free download study guide, some exercises and answers about Oracle certification 1Z1-466 exam as an attempt.
In recent years, fierce competition agitates the forwarding IT industry in the world. And IT certification has become a necessity. If you want to get a good improvement in your career, The method that using the IT-Tests.com’s Oracle 1Z1-466 exam training materials to obtain a certificate is very feasible. Our exam materials are including all the questions which the exam required. So the materials will be able to help you to pass the exam.
Related study materials proved that to pass the Oracle 1Z1-466 exam certification is very difficult. But do not be afraid, IT-Tests.com have many IT experts who have plentiful experience. After years of hard work they have created the most advanced Oracle 1Z1-466 exam training materials. IT-Tests.com have the best resource provided for you to pass the exam. Does not require much effort, you can get a high score. Choose the IT-Tests.com's Oracle 1Z1-466 exam training materials for your exam is very helpful.
1Z1-466 (Project Lifecycle Management Essentials) Free Demo Download: http://www.it-tests.com/1Z1-466.html
NO.1 Which is the type of closure described as the mechanical an analytical step associated with the
closure of a project or phase?
A. Contractual
B. Typical
C. Intra-business
D. Conventional
Answer: A
Oracle exam simulations 1Z1-466 1Z1-466
NO.2 Tasks in the Project Execution and Control phase are ongoing. How often they are executed?
A. In each iteration
B. Three times
C. Five times
D. At the beginning of each week
E. As needed
Answer: A
Oracle 1Z1-466 questions 1Z1-466 demo 1Z1-466 dumps
NO.3 What is not true about planning in OUM?
A. OUM has been developed with the intent that the approach for a given project be built up from a
core set of activities.
B. Projects should be tailored down from the full OUM work breakdown structures.
C. OUM takes an iterative and incremental approach to planning a project.
D. Tasks within OUM are considered place holders for work.
Answer: D
Oracle 1Z1-466 exam prep 1Z1-466 pdf 1Z1-466
Explanation:
Incorrect: Not A:OUM is designed to support a broad range of project types. As such, it must be
flexible andscalable. The appropriate point of balance for a given project will vary based on a
number of project risk and scale factors. The method has been developed with the intent that the
approach for a given project be "built up" from a core set of activities to implement an appropriate
level of discipline, rather than "tailored down".
Not C:OUM recognizes the advantages of an iterative and incremental approach to development
and deployment of information systems. Any of the tasks within OUM may be iterated. Whether or
not to iterate, as well as the number of iterations, varies. Tasks may be iterated to increase quality of
the work products to a desired level, to add sufficient level of detail, or to refine and expand the
work products on the basis of user feedback.
NO.4 At the end of iteration phase, during Project Execution and Control, which three key tasks
should be conducted?
A. QM.050 Perform Quality Assurance
B. WM.050 ManageApprovals
C. CMM.030 Manage Project Team Communication
D. PKM.020 Conduct Baseline Risk Assessment
E. SM.060 Close Scope management
F. PKM.060 Conduct Post-Production Risk Assessment
G. OCHM.040 Establish Follow-Up process
Answer: A,B,C
Oracle 1Z1-466 1Z1-466 1Z1-466
NO.5 What is not true about risk management in OUM Manage?
A. The project manager should regularly conduct risk assessments.
B. Risks become even more critical during the Project Execution and Control Phase.
C. Particular attention should be paid to risks prior to production cutover.
D. If a baseline risk assessment is done during the Project Startup phase, there are no further risk
assessment required on the project.
Answer: D
Oracle study guide 1Z1-466 dumps 1Z1-466 practice test 1Z1-466 1Z1-466 1Z1-466 test answers
NO.6 What describes the nature of the activities within the Project Execution and Control phase?
A. They are dependent upon one another.
B. They are dependent upon earned value.
C. They are ongoing.
D. They are grouped according to priority.
Answer: A
Oracle study guide 1Z1-466 1Z1-466 1Z1-466 1Z1-466 exam simulations 1Z1-466
NO.7 Select the three key project roles as prescribed by OUM Manage.
A. Stakeholder
B. Change Control Board
C. Issue Review Board
D. Project Team
E. Testing Committee
Answer: A,B,D
Oracle 1Z1-466 1Z1-466 answers real questions 1Z1-466 original questions 1Z1-466 answers real questions
Explanation:
A:Project managers use OUM to make sure they and their stakeholders develop a shared
understanding of what is needed, choose an appropriate architecture, and transfer the ownership of
the end-product to the stakeholders.
B:CCB(Change Control Board)is a review committee that discusses and approves requests for
changes to On Demand customer system configurations. The change requests are fulfilled in the
following ways:
A work guideline is generated by engineering for operations to use and implement.
The changes are included in Oracle Certified Configurations.
D:Project teams to take advantage of this experience by
NO.8 Which is true about OUM Manage?
A. It emphasizes clearly documenting the scope of the project and the exact procedures to
implement changes to this scope.
B. It is not possible to control the project timeline without a detailed project plan.
C. It is necessary to only document the items in the scope.
D. If the project sponsor requires a functional change, the project team must comply with the
request.
Answer: A
Oracle exam dumps 1Z1-466 1Z1-466 exam 1Z1-466 dumps
Explanation:
The Manage focus area is organized into 13 processes: Bid Transition (A)Scope Management
Financial Management
Work Management Risk Management Issue and Problem Management Staff Management
Communication Management Quality Management Configuration Management Infrastructure
Management Procurement Management Organizational Change Management
Collectively, these processes form a comprehensive set of tasks required to manage Oracle-based
development and implementation projects. Every project includes most, if not all, of these
processes, whether they are the responsibility of a consulting organization, a client organization, or
a third party.
NO.9 According to the recommended training for this exam, what is the definition of a project?
A. A sequence of tasks with a beginning and an end, bound by time, responses, and desired results
B. Anything for which there is an executed contact
C. A sequence of tasks for there is a Statement work
D. A sequence of tasks with a specified end date
Answer: A
Oracle 1Z1-466 certification 1Z1-466
IT-Tests.com offer the latest 1z0-593 Questions & Answers and high-quality HP2-E58 PDF Practice Test. Our MB2-866 VCE testing engine and 1z0-559 study guide can help you pass the real exam. High-quality CAT-440 Real Exam Questions can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.
Article Link: http://www.it-tests.com/1Z1-466.html
没有评论: